Multifamily flooring takeoffs, by unit type.
We take off each unit type, count how many of each the plans show, and total the quantities for the building. You get the sheet by unit type and the building totals for every flooring material on the plans, with carpet ordered from a seam layout in every type that has it.
An example building
Here is how a three-type building counts. The building is made up for the sample. Plan B is our sample unit, so its numbers match the sample takeoff.
24 units puts this job at 1 credit.
When the units and the square feet put a job in different sizes, the larger one sets the credit count. If this building's flooring ran past 25,000 SF, the square feet would set the count instead.
| Unit type | Count | Note |
|---|---|---|
| Plan A, 1 bed / 1 bath | 8 | Made up for the sample, taken off the same way |
| Plan B, 2 bed / 1 bath | 8 | Our sample unit, quantities below |
| Plan C, 2 bed / 2 bath | 8 | Made up for the sample, taken off the same way |
| Building | 24 | 1 credit |
| Line | One unit | x 8 |
|---|---|---|
| LVT, net | 453 SF | 3,624 SF |
| Carpet, ordered from the seam layout | 59 SY | 472 SY |
| Floor tile, net | 91.9 SF | 735.2 SF |
| Rubber cove base, net | 22.8 LF | 182.4 LF |
| Transitions | 3 EA | 24 EA |
| Base cabinets | 4 EA | 32 EA |
How units set the credit count
Every takeoff runs on credits. On multifamily jobs the unit count usually decides it. A credit costs $78 to $175, depending on your plan.
- Up to 30 units or 25,000 SF
- 1 credit
- 31 to 90 units or up to 75,000 SF
- 2 credits
- 91 to 180 units or up to 150,000 SF
- 3 credits
- Anything bigger
- We quote it
What you get back
- Marked-up plans for each unit type, color coded by material
- An Excel sheet by unit type, with net and order quantities and the waste factor on each line
- Building totals for every material
- A carpet seam layout on 12 ft rolls for each unit type with carpet
- Countertops, cabinets and wall tile by unit type, if you add them (+1 credit)
- A list of every assumption we made
Try it on a building you are bidding now, or one you already measured. Your first job up to 30 units or 25,000 SF is free.
Multifamily questions
Do you take off every unit or each unit type?
Each unit type. We measure it, count how many of that type the plans show, and total the quantities for the building. You get both: the sheet by unit type and the building totals.
How many credits is a multifamily job?
Count the units. Up to 30 units is 1 credit, 31 to 90 units is 2 credits, 91 to 180 units is 3 credits, and we quote anything bigger. A 66-unit building is 2 credits. The square feet count too: when the units and the square feet put a job in different sizes, the larger one wins. How credits work
Can you add countertops and cabinets by unit type?
Yes. Countertops, cabinets and wall tile add 1 credit to the job, with counts for each unit type and totals for the building.
Try it on one building
Your first building up to 30 units or 25,000 SF is free, whether you already measured it or are bidding it now. We measure it without seeing your numbers and your files come back in 24 hours. Then our lead estimator goes through it with you on a 15-minute review call.
Plan changes and anything we missed are fixed free, every time, on the same project.